page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52 page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
50 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
4.3.4 DESIGN PROCEDURE
The headrace canal design procedure is as follows:
1. Decide on canal type as per site conditions (e.g. earth canal,
stone masonry in mud mortar or stone masonry in cement
mortar).
2. Choose a suitable velocity (V) such that it is less than the
maximum velocity given in Table 4.1. Note that
unacceptable headloss may result if chosen velocities are
close to maximum velocity. Also choose the
corresponding roughness coefficient (n) from Table 4.1.
Then calculate cross-sectional area (A) from the following
equation:
A = Q/V
3. Using Table 4.2 decide on the side slope (N). Note that N is the
ratio of the horizontal length divided by the vertical height of
the side wall ( i.e., N = h/v as shown in Figure 4.6 ).
X = 2 (1+N2) - 2N
H=
A
X+N
B = HX
T = B + (2HN)
4. Calculate the optimum canal height (H), canal bed width
(B), and the canal top width (T) using the following
equations:
Note that in case of a rectangular canal, N = 0 and X = 2,
so:
H = A/2 and T = B = 2xH
Hence, for a rectangular canal the hydraulically optimum shape
is when the width is twice the height. These symbols are
schematically shown in Figure 4.6.
If an optimum canal shape is not possible due to site specific
conditions (such as narrow width along a cliff) then either
the width or the height should be selected to suit the
conditions. Then the other dimension can be calculated.
5. To ensure stable and uniform flow in a the velocity must be
less than 80% of the " critical velocity limit" Vc = Ag/2
where Vc is the critical velocity. Note that for a rectangular
canal Vc = Hg
6. Calculate the wetted perimeter (P) using the following
equation
P = B + 2H (1 + N2) note that for a rectangular canal,
P = B + 2H
7. Calculate the hydraulic radius (R) as follows: R = A/P
8. The slope (S) can now be found from Manning’s equation:
s = (nV/R0.667)2
Now all dimensions required for the construction of the
canal are known.
9. Headless = L S (L is the length of the canal section).
Sometimes S is fixed by the canal route, which has already
been decided and surveyed. Another example of fixed slope
(S) situation is when an existing irrigation canal is proposed
to be used for a micro-hydro scheme (and higher flows as
well as less leakage are required). In such situations different
cross sectional area should be assumed (i.e., trial and error)
such that the velocity is less than the allowable maximum
velocity for the design flow and the type of canal proposed.
This can be done by rewriting Manning’s equation as
follows:
Q
=n([BBH
+
+
NH2)5/3 S
2H (1+n2)
]2/3
With a known design flow (Q), select the appropriate side
slope (N) according to the type of canal chosen. Then fix
either B or H and calculate the other using the above
equation. Finally from Table4.1, check that the velocity for
the canal type.
10.Calculate the size of the largest particle that will be
transported in the canal:
d = 11 R S
• Water level being above the design level due to
obstruction that for a rectangular canal V = Hg
If this is less than the possible size in the canal, repeat the
design using a higher velocity.
11.Allow a freeboard as follows:
300mm for Q<500 1/s
400mm for 500 1/s < Q < 1000 1/s (such flows are unusual
for micro-hydro shcemes).
Such freeboard allows for:
Uncertainties in the design (e.g. the value of *n* may differ
by 5% to 10% from estimate).
Water level being above the design level due to obstruction
in the canal or during emergencies.
Deterioration of the canal embankment.
12. Check that possible flood flow in canal can be accommo-
dated without using more than 50% of the freeboard.
13. Find the total head loss. If this is too high or too small,
repeat the calculations with a different velocity. Consider
using different types of canal keeping the overall cost in
mind.
Avoid a canal width of less than 300 mm as narrow canals can be
easily blocked. Also for stone masonary canals, smaller sizes
are difficult to construct.